Construction Update – July 18

It’s a very exciting time to visit Elizabeth Quay!

Last week, Chevron Australia confirmed that they will be building their new HQ within Elizabeth Quay to house their 4,000 staff. The development will signal a huge step forward for the building out of Elizabeth Quay.

Please see below for a progress update and interior designer recommendations:

LOT 10: 
Probuild have advised practical completion at the end of March 2019. 
We are therefore expecting:
– Client inspections in April 2019
– Settlement in May 2019

LOT 9: (The Ritz-Carlton)
Probuild have advised practical completion at the end of May 2019.
We are therefore expecting:
– Client inspections in June 2019.
– Settlement in July 2019. 

Please note: These dates are not guaranteed. There may be unforeseen delays in construction and producing apartment titles. 

  • Concrete pours are now up to level 22 in Lot 10 and level 16 in Lot 9.
  • Glass is now being installed on Lot 9 & 10 and services are being added to both towers.

Feel free to get in contact should you have any questions by emailing thetowers@perth.prd.com.au, call 1800 Towers or visit www.thetowersperth.com.au

The photos in this report were taken in July 2018.

4d69db0b-c736-462c-8b2b-698272734444
Aerial photograph overlooking Lot 10 works
aa3a1604-56c4-47f1-b15f-02904d6e1c22
Aerial photograph overlooking Lot 9 works and site accommodation
45333a54-fb41-485a-8b4c-6feb9c1aba65
View of project using Elizabeth Quay time-lapse camera

Share this

DATA ROOM LOG-IN

If you are a Sales Agent for The Towers at Elizabeth Quay and require access to our Data Room, please call 1800 TOWERS.